    We’re doing a big spring refresh with new signage, a new window and a new mat at both registers with our spring message. The refresh starts on a fixed date, because we’re running it with the arts festival downtown.

    My question: once I approve the proof, how long until mats are actually on my counter? I want to work backward from the festival date so I’m not that person refreshing the tracking page the night before.

    #5364
    EventMktg_SanJose
    Participant

    Working backward is exactly right. I do this for six trade shows a year, and the proof is almost never the slow part. Approval is. Here’s my rule: count the days your own team needs to say yes, then double it.

    At my company, a trade show mat goes past the event lead, the brand team and sometimes legal if it has a product claim on it. Each of them takes a day or two, and someone is always on vacation. The printer is usually waiting on us, not the other way around.

    My timeline, from the date the mats must be in hand:
    – Shipping time to your address
    – Production time after proof approval
    – Your approval time, doubled
    – Proof turnaround
    – Artwork final, with text checked by someone who didn’t write it

    #5365
    GiftShop_Asheville
    Participant

    Doubling the approval time is painfully accurate. My business partner takes a weekend to answer anything. And the festival date doesn’t move, so I can’t let it slide like I usually do with the window.

    #5366

    For multiple locations, add a step: the store list. Before a rollout, I confirm the delivery address for every store, the name of whoever receives deliveries and whether the dock is open on Saturdays. One wrong address cost us a week once, because the carton went back to the sender.

    For a single shop, double-check that the address on the order has your suite number. Downtown deliveries go to the wrong door all the time.

    #5367
    BikeShop_Boise
    Participant

    Newbie question. What happens if you see a mistake on the proof? Does the clock restart?

    #5368
    EventMktg_SanJose
    Participant

    In my experience, yes. Production time counts from the approved proof, not from the first one. Every round of changes pushes the whole schedule. That’s why the text check happens before the artwork goes out, not after.

    My checklist for the proof itself: spelling of every word, phone number and web address typed out and checked, dates and prices on the mat, logo color, and anything near the edge. I read it out loud once. You catch more mistakes by ear than by eye, especially in your own copy.

    #5369
    CounterMats Team
    Moderator

    Good planning advice, especially counting from the approved proof and doubling your own approval time.

    Here’s our side of the timeline. We send a free digital proof within 1 business day. Printed mats ship 5 business days after proof approval, for orders up to 2,500 mats. If the date is tight, a 3-business-day rush is available on most printed orders; ask for the rush cost with your quote. Larger orders ship free by ground to the lower 48 states. Transit time depends on the destination, so add the carrier’s ground time for your ZIP code at the end.

    And yes, the 5 business days count from the approved proof, so a change after the first proof moves the ship date.

    What happens between order and finished mat: https://countermats.com/custom-counter-mats-turnaround/

    CounterMats Team · Contact Us

    #5370
    GiftShop_Asheville
    Participant

    Counting backward with all of that, I need final artwork about three weeks before the festival to feel calm. I set myself a reminder for four weeks before, because of my partner.

    #5371
    EventMktg_SanJose
    Participant

    Four weeks is smart. I always keep a few days of slack for something I can’t control, like a storm closing a hub or a weekend falling in the wrong spot. The slack is cheap insurance. Paying extra to rush a job because you lost a week to approvals is the expensive way to learn it.

    #5372

    One more tip: ask for tracking to go to whoever is in the store that day, not just to you. If you’re at the festival setting up a booth, someone at the shop needs to know the box is coming.

    #5373
    BikeShop_Boise
    Participant

    Writing all of this down. I have an opening date too, and I hadn’t planned for proof rounds at all. Is there anything else people usually forget?

    #5374

    Holidays. Production and shipping schedules usually skip weekends and holidays, and carriers slow down around them. If your date sits right after a long weekend, start earlier than the math says. Also, someone has to be at the store when the box shows up, so check the delivery day against your own hours.

    And plan for the install. Mats arrive flat in a box, but somebody still has to clear the counter, wipe it down, place them and move the old stuff out. For one shop that’s an hour. For a rollout, it’s a task on every store manager’s list, and it needs a date like everything else.

    #5375
    GiftShop_Asheville
    Participant

    Update for anyone planning around a date. I locked the final artwork four weeks before the festival, and my partner signed off on the text in one round. The trick was giving him a deadline instead of a question: “I send this Friday unless you object.” The rest of the refresh plan runs off the same calendar now.

    #5376
    EventMktg_SanJose
    Participant

    “I send this Friday unless you object” is going in my playbook. Enjoy the festival.

    #5377

    One round of comments from a business partner is the real headline here.

Viewing 15 posts - 1 through 15 (of 15 total)
  • Log in or create an account to post. Anyone can read.

Log in

Forgot your password?

Join the Counter Mat Forum

Everyone sees this. A role works well instead of your name, for example CStore_Owner_Ohio.

Members, discussions and dates in threads marked Example thread are fictional. CounterMats wrote them to explain common counter mat questions in plain language.

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.