Lead time on 1,000 mats for a chain rollout?

Example thread · fictional members and dates What does this mean?

Viewing 16 posts - 1 through 16 (of 16 total)
  • Author
    Posts
  • #5347

    Our parent group is rolling one counter design across three restaurant brands in March. With registers, pickup counters and spares, it comes to about 1,000 mats going to a little over 300 addresses.

    Our 38-shop rollouts were manageable. This one isn’t. The other two brands have their own store lists, their own field teams and different counter layouts, and nobody has ever counted their registers in one place. How far back from launch day should the planning start, and where do rollouts this size usually slip?

    #5348
    PromoBuyer_Chicago
    Participant

    They almost never slip in production. They slip before and after. Before, it’s approvals and the store list. After, it’s freight and receiving.

    Start with the store list, because everything else depends on it. Every address, a contact name, receiving hours and how many mats each counter needs. On a list of 300 addresses, expect a few dozen to be wrong on the first pass.

    Keep the list in one spreadsheet with one owner. The moment two versions exist, someone ships to the old one.

    #5349
    TradeMktg_Atlanta
    Participant

    Our placements run to several hundred stores at a time, and the list is always the problem. Closed stores, moved stores, a manager who says two registers when there are three. We send the list to the field team and ask them to confirm counts at each location before we count mats. Ask for a photo of each counter while you’re at it.

    Give that step two full weeks. People answer late.

    #5350

    Two weeks for the list, noted. On approvals: three brands means three brand teams. Each one will want to see the proof.

    #5351
    PromoBuyer_Chicago
    Participant

    Then get all three in one review. Send the proof to everyone at once with a deadline and one person who collects the comments. Three separate reviews in a row will cost you more time than production.

    And agree on who decides when two brand teams disagree. That conversation always happens, so have it before the proof shows up.

    #5352
    TradeMktg_Atlanta
    Participant

    On freight, decide early between shipping straight to each store or to a warehouse that sends the mats on. Direct is faster but means 300 tracking numbers. A warehouse adds a step but lets you check the cartons and pack them with the rest of the launch kit.

    We ship to our distribution center and the mats go out on the regular delivery trucks with the product. Nobody has to receive an extra box.

    It does mean the mats have to reach the distribution center earlier, because the trucks run on a fixed schedule. Miss the truck by a day and a store waits a week.

    #5353

    That’s the option I hadn’t thought of. Our food distributor already visits every store weekly. If the mats go on that truck, the store team sees one delivery, not two.

    #5354
    CounterMats Team
    Moderator

    PromoBuyer_Chicago is right that the time goes before and after production, and our lead-time page makes the same case.

    It walks through why the clock doesn’t start when you think it does, why proofing is the checkpoint that saves the schedule, why production is the part people worry about and shouldn’t, the queue you can’t see, and why shipping is the stage everyone forgets to ask about.

    For our part, every printed order gets a free digital proof within 1 business day. Printed mats ship 5 business days after proof approval, for orders up to 2,500 mats, so your quantity sits inside that window. If the date gets tight, a 3-business-day rush is available on most printed orders; ask for the rush cost with your quote. Larger orders ship free by ground to the lower 48 states. Tell us in the quote request whether the mats go to one warehouse or many addresses.

    What happens between your PO and the pallet: https://countermats.com/bulk-counter-mat-lead-time/

    CounterMats Team · Contact Us

    #5355

    So production isn’t the long pole. Working backward from a March launch, here’s my draft: mats at the distribution center three weeks before launch so they ride the regular trucks, proof approved a few weeks before that, three-brand review two weeks, store list two weeks, artwork final before any of it.

    #5356
    PromoBuyer_Chicago
    Participant

    Add a buffer between the proof and the truck. If the review drags, the buffer is the only thing that keeps the launch date. I keep two weeks of slack in any rollout of this size.

    Also plan a holiday check. Your schedule crosses the end of the year, and a lot of approvers disappear between Christmas and New Year’s Day.

    #5357
    TradeMktg_Atlanta
    Participant

    And count the spares by region, not just in total. If a mat gets damaged in a store in Ohio, the spare should be in the Ohio warehouse, not at headquarters.

    #5358

    Spares by region, yes. We’ll hold them at each distribution center, about one spare for every twenty mats, which is what our last rollout used up in the first six months.

    The holiday point is real. Two of our brand leads are out the last two weeks of December. So the review has to finish before the 19th, or it moves to January.

    #5359
    PromoBuyer_Chicago
    Participant

    Then pull it forward. Send the proof for review the week of the 15th with a hard deadline of the 18th. People respond faster before a holiday than after one.

    #5360
    TradeMktg_Atlanta
    Participant

    One more thing from our placements: give the stores an install note. A short card in each carton saying where the mat goes and what to do with the old one. Without it, a third of the mats end up under the counter, still in plastic. We also add a photo of a correctly placed mat. One picture saves a lot of phone calls.

    #5361

    Install card goes in the launch kit. Final plan: store list confirmed by January 9, proof review closed before the holidays or the second week of January, two weeks of slack, mats at the distribution centers three weeks before launch. Thanks for walking me through the parts that aren’t production.

    #5362
    PromoBuyer_Chicago
    Participant

    That plan has slack in the right places. Good luck with three brand teams in one room. Post how it went after launch. Rollouts across brands are rare enough that the next person here will want the real timeline, not the plan.

Viewing 16 posts - 1 through 16 (of 16 total)
  • Log in or create an account to post. Anyone can read.

Log in

Forgot your password?

Join the Counter Mat Forum

Everyone sees this. A role works well instead of your name, for example CStore_Owner_Ohio.

Members, discussions and dates in threads marked Example thread are fictional. CounterMats wrote them to explain common counter mat questions in plain language.

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.