  • in reply to: Shipping mats to stores in different states: one box or many? #5766

    That’s our playbook almost word for word. Add a spare count per region. One damaged box in Tennessee shouldn’t mean a reprint.

    in reply to: Shipping mats to stores in different states: one box or many? #5762

    Yes. And build a check-in step. Every store replies to the heads-up email when the box is in, with a photo of the mat on the counter. We chase the ones that don’t reply after a week. On our last rollout that caught four stores with a box sitting unopened.

    in reply to: Shipping mats to stores in different states: one box or many? #5758

    Usually yes on paper, no once you count the reps’ time. One pallet to a warehouse looks cheap until you add gas, hours and the three weeks you just described. Ask the printer to quote both ways and compare against what the last rollout really cost you.

    Timing is the bigger win for your case. Direct shipments go out within a day or two of each other, so every store has its mats in the same week. With reps driving, the last store on the route gets them three weeks after the first. For a promo tied to a TV date, that alone decides it.

    in reply to: Shipping mats to stores in different states: one box or many? #5755

    Then tell them before the box shows up, or it goes in the back room and never comes out. We send a short email to each store a week out: what’s coming, what it looks like, where it goes on the counter, who to call if it’s damaged.

    For independents, I’d also put a one-page note inside each box. Same four points, plus a photo of the mat on a counter. The person who opens the box is rarely the person who read the email.

    in reply to: Shipping mats to stores in different states: one box or many? #5753

    We do direct-to-store for every rollout now. It works, but only with a clean store list. Every bad address on the list becomes a mat that sits at a carrier depot.

    Our list has these columns: store number, store name, street address, contact name, phone, delivery hours, how many mats. Delivery hours matter more than people expect. A store in a strip mall that only takes deliveries before 10 a.m. will refuse a box at 2 p.m.

    in reply to: Will our brand red print the same across 30 stores? #5718

    Doing that. And store 11 gets new bulbs before the mats go in.

    in reply to: Will our brand red print the same across 30 stores? #5716

    Pulling this together for our marketing folder:

    • Vector file with the CMYK build from the guide and the Pantone number in the notes
    • Ask the printer which one they print to on mats
    • One run, one file, one material, all 38 stores
    • Hold the remodel stores’ mats until they open
    • Keep a reference mat in a sleeve, out of the sun
    • Compare complaints against the reference in the same light
    • Master file named, dated and locked
    in reply to: Will our brand red print the same across 30 stores? #5712

    Order everything, ship in waves. That’s the part I didn’t know was an option.

    Designer_PDX, still curious about the lighting question. Our brand team will ask.

    in reply to: Will our brand red print the same across 30 stores? #5710

    That would have saved me six weeks of photos from store 11. Their lighting is warm LED. Everything in that store looks orange, including the sandwiches.

    Which raises a question for Designer_PDX. If the stores have different lighting, is there any point chasing a perfect match? Or do I just accept that store 11 will always look a little warmer?

    in reply to: Will our brand red print the same across 30 stores? #5707

    So the spring batch is the real risk. Eight stores, six months later.

    in reply to: Will our brand red print the same across 30 stores? #5704

    The guide has a Pantone number and a CMYK build. I’m not sure anyone has sent the printer anything but a PNG, though.

    Finance signed off. Now the hard part: getting 40 managers to confirm their register counts by Friday. I’m sending it as a one-question form, not an email, so nobody can reply with a story.

    Here’s what I’m taking to finance: one central PO, one design, a line per store on the invoice, store numbers on every carton, everything to the distribution center and out on the weekly trucks. Franchisees get charged back through the usual monthly statement.

    Fifty is no issue for us. Forty stores, and some have three registers, so we’re well past it before we count spares.

    We have a distribution center that already sends weekly trucks to every store. Putting mats on the truck costs us almost nothing.

    That’s the store eleven problem. Store eleven always looks different, because whatever is meant for it ends up somewhere else.

    A line per location on the invoice would make finance happy. Is that something printers usually do?

    in reply to: Lead time on 1,000 mats for a chain rollout? #5361

    Install card goes in the launch kit. Final plan: store list confirmed by January 9, proof review closed before the holidays or the second week of January, two weeks of slack, mats at the distribution centers three weeks before launch. Thanks for walking me through the parts that aren’t production.

    in reply to: Lead time on 1,000 mats for a chain rollout? #5358

    Spares by region, yes. We’ll hold them at each distribution center, about one spare for every twenty mats, which is what our last rollout used up in the first six months.

    The holiday point is real. Two of our brand leads are out the last two weeks of December. So the review has to finish before the 19th, or it moves to January.

    in reply to: Lead time on 1,000 mats for a chain rollout? #5355

    So production isn’t the long pole. Working backward from a March launch, here’s my draft: mats at the distribution center three weeks before launch so they ride the regular trucks, proof approved a few weeks before that, three-brand review two weeks, store list two weeks, artwork final before any of it.

    in reply to: Lead time on 1,000 mats for a chain rollout? #5353

    That’s the option I hadn’t thought of. Our food distributor already visits every store weekly. If the mats go on that truck, the store team sees one delivery, not two.

    in reply to: Lead time on 1,000 mats for a chain rollout? #5350

    Two weeks for the list, noted. On approvals: three brands means three brand teams. Each one will want to see the proof.

    in reply to: What does a custom printed mat cost per piece at 100? #5266

    And get the store list right before you count. Our first rollout came up short because two stores had a second register nobody mentioned. Now every manager confirms their register count in writing before we count mats.

    in reply to: What does a custom printed mat cost per piece at 100? #5261

    Don’t forget the reorder price. We change the seasonal message four times a year. If the first run carries a setup cost and every reprint carries it again, the annual cost doubles fast. Ask what a reprint with a new message costs before you sign anything.

    in reply to: What does a custom printed mat cost per piece at 100? #5255

    Shipping is the line people skip. We run 38 locations. A quote that looks good for one delivery to our office gets much worse when the mats have to go to 38 addresses. Ask whether the price is for one ship-to or many, and who splits the cartons.

    When we ship to one address and split it ourselves, somebody on my team spends two days repacking boxes and printing labels. That’s real cost even if it never shows up on the quote. When mats go straight to each store, I also need to know how they’re packed, because a store manager who finds a bent mat in a crushed box will just put it out anyway.

    in reply to: What should I check on a proof before I approve it? #5329

    Our routine from now on, for anyone who wants it. Two people check the proof separately. One reads every word out loud. One calls every phone number and types every web address. The person who wrote the text is never the only checker. Compliance signs off on the proof, not the draft. One person sends one reply with every change.

    in reply to: What should I check on a proof before I approve it? #5325

    Same here now. And if a design has store-specific parts, like a phone number per store, every variant gets its own check. We had one shared layout with 38 phone numbers. Checking the layout once isn’t checking the numbers.

    For those, we print a list of every variant with the store number and phone number side by side and tick each one off against the proof. It’s boring, and it’s the only way we’ve found that works.

    in reply to: What should I check on a proof before I approve it? #5320

    The version check would have saved us last time. The proof looked right, but it was built from the file before legal changed one line. Now the file name carries a version number, and the proof email has to name it. If a proof doesn’t say which version it was built from, we send it back before anyone reads a word.

    in reply to: How long from approved proof to mats on the counter? #5377

    One round of comments from a business partner is the real headline here.

    in reply to: How long from approved proof to mats on the counter? #5374

    Holidays. Production and shipping schedules usually skip weekends and holidays, and carriers slow down around them. If your date sits right after a long weekend, start earlier than the math says. Also, someone has to be at the store when the box shows up, so check the delivery day against your own hours.

    And plan for the install. Mats arrive flat in a box, but somebody still has to clear the counter, wipe it down, place them and move the old stuff out. For one shop that’s an hour. For a rollout, it’s a task on every store manager’s list, and it needs a date like everything else.

Viewing 30 posts - 1 through 30 (of 32 total)

Members, discussions and dates in threads marked Example thread are fictional. CounterMats wrote them to explain common counter mat questions in plain language.

Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.